Formwork• Two symmetrical shells with bottom plates, assembled with quick assembly bolting system
• The inside of the shells is architectured by means of appropriate coatings
• ECOPODE™ moulds are specially made of fibre glass shells to obtain the rock-like appearance, backed with a steel spider frame mounted on wheels.
Casting • Min. area required to cast one unit of height H:
2H2• Min. compressive concrete strength recommended at stripping:
10 MPa for all units sizes
• Typical daily standard production rate: one unit per mould
Handling • Forklifting is effective for handling units up to 3 m
3• Large units are handled with slings
• Min. compressive concrete strength recommended for handling units:
25 MPa for units less or equal to 8 m
3
and 30 MPa for sizes above 8 m
3 Storage • ECOPODE™ units are stored on one level placed close to each other, on ground with a sufficient bearing capacity.
• Min. area required to store 10 units of height H:
7.1 H2Placement The positioning principle is based on a predetermined grid aimed at achieving optimum keying of the units. The grid spacings will match those of the smooth skin ACCROPODE™ II underneath.
Placement above water level is carried out visually or using GPS in order to obtain the proper packing.
Placement rates
|
Average placing time per unit (using cable cranes) |
|
1.0 m3 £ Unit volume £ 3.0 m3 |
6 to 8 mins |
|
4.0 m3 £ Unit volume £ 8.0 m3 |
10 to 12 mins |
|
8.0 m3 £ Unit volume £ 11.0 m3 |
12 to 15 mins |
NB: Higher rates can be obtained using hydraulic placing equipment with small size units